| 1 |
Opening of holes on the floor slab for installation, then filling of the holes. |
| 2 |
Setting of beams for installation. |
| 3 |
Opening of holes on either floor slab or beam sleeve for Moving SideWalk carrying-in, then filling of the holes. |
| 4 |
Construction of Moving SideWalk pit on the bottom floor and water-proofing. In case there is a space in use (room,etc.) under the pit/machine room, fire-proofing of the pit. |
| 5 |
Finishing (mortar finish etc.) of floor and ceiling around Moving SideWalk after the installation. |
| 6 |
Construction of handrails, walls, etc. around Moving SideWalk. |
| 7 |
External finishing of Moving SideWalk. |
| 8 |
Setting of guard plates (only for inclined type). |
| 9 |
In case there is a stairwell between Moving SideWalks, setting of intermediate hanging wall, ceiling, handrails and fences. |
| 10 |
Joint work of Moving SideWalk and ceiling. |
| 11 |
In case there is a stairwell between Moving SideWalks or Moving SideWalk and floor, setting of safety net, etc. |
| 12 |
In case of installation to an existing building, preparation of carrying-in entrance and filling of it. |
| 13 |
In case of installation to an existing building, protection work around Moving SideWalk and of carrying-in route. |
| 14 |
In case Moving SideWalk operating panel is to be installed on building wall, drilling of holes. |
| 15 |
Setting of barrier plates to prevent children from climbing deckboard up. |